Evidence-led audits make better proposals and estimates

Most estimate disputes start with an assumption nobody could trace. Part 5 of Technology Health Check shows how evidence from a health check flows into a request for proposal, a supplier's assumptions and a price, and how it catches the contradictions between architecture, scope, schedule, cost and acceptance before anyone signs.

#Technology Health Check#Proposal Strategy#Tender Enablement#Solution Architecture

Every technology contract that ends in a dispute has a moment, usually months in, when someone produces the original proposal and reads out an assumption. "Integration with existing systems is limited to three interfaces." The supplier says that was the basis of the price. The client says there were always seven. Both are telling the truth as they understood it, and neither can show where their number came from.

That dispute was not caused by bad faith or bad estimating. It was caused by an estimate built on a description of the current state that nobody had checked. The fix is unglamorous: before anyone writes a proposal or a price, establish the facts the price depends on, from evidence, and carry them through every document so that a reviewer can trace each line back to its source.

Cedarberg Logistics is fictional, and its systems and figures are illustrative. The health check in Part 1 and the gap analysis in Part 2 gave the Cape Town cold-chain firm something most organisations going to market do not have: an evidence file describing its current estate. This part follows what that did to its request for proposal for a live temperature-visibility platform, and to the bids it received.

Where estimates usually come from

A typical request for proposal describes the current state from the latest architecture document, a few workshops and the memory of whoever is writing it. Suppliers then estimate against that description, adding contingency for what they suspect is missing. The client compares prices that rest on different guesses about the same estate, picks one, and discovers the real estate during delivery.

Cedarberg's own architecture document, the newest of three conflicting diagrams found in Part 3, showed three integrations around the transport management system. The health check had counted seven live ones: the telematics platform, the warehouse management system, the finance system, the customer portal, the data warehouse, an email and SMS notification service, and a scheduled export to one large customer. Four of the seven were not in any document.

Had the request gone out describing three, every bid would have been priced against an estate that did not exist.

Carry one counted fact all the way through

The discipline is simple to state. Each material fact about the current state is established from evidence once, given an identifier, and then referenced, not restated, wherever it drives a decision.

One counted fact, carried all the way to the contractFinding: 7 liveintegrationsAssumption: all 7stay in scopeScope: 7 interfacebuilds or rewiresAcceptance: 7interfaces testedPrice: built fromthe same 7Effort: a rangeper interfaceEVERY LINE OF THE ESTIMATE POINTS BACK TO THE FINDING
The health check counted seven live integrations where the old architecture document showed three. When the same number drives the assumption, the scope, the effort range, the price and the acceptance criteria, a reviewer can trace every line of the estimate back to evidence. Figures are illustrative.

For Cedarberg, the integration count became a single traceable chain:

  • Finding. Seven live integrations, with the configuration exports as evidence.
  • Assumption. The request for proposal stated that all seven remained in scope and listed them.
  • Scope. Each became a scope item: rebuild, rewire through the new platform, or leave untouched and test for regression.
  • Effort. Suppliers were asked to estimate each scope item separately, as a range, rather than a single integration line.
  • Price. The commercial schedule priced the same seven items, so the price and the scope could not drift apart.
  • Acceptance. The acceptance criteria named the same seven interfaces and the test each had to pass.

When one of the bidders queried the scheduled export to a large customer, Cedarberg could answer in a day, with evidence, instead of issuing a vague clarification. The same structure is the client-side mirror of the supplier discipline described in architecture and price must describe the same solution.

Contradictions are cheaper before the bid

Evidence does a second job. It exposes contradictions between the documents that are meant to describe the same programme. Most organisations write the architecture, the scope, the schedule, the business case and the acceptance criteria at different times, with different authors. Each is internally reasonable. Together they disagree.

Four contradictions found before the request for proposalONE ARTEFACT SAYSANOTHER SAYSCONTRADICTIONARCHITECTURE3 integrationsHEALTH CHECK7 live interfacesScope too smallSCHEDULECutover in a weekendOPERATIONSDepots run 24/7No cutover windowCOSTLicences for 120 usersSCOPEAll 180 drivers use itLicences shortACCEPTANCEData within 5 minutesARCHITECTURENightly file transferCannot be met
Each row pairs two artefacts that describe the same programme and disagree. Found during a review, each costs a meeting. Found after contract award, each becomes a change request or a dispute. Values are illustrative.

Cedarberg's pre-release review found four:

  1. Architecture against evidence. The design assumed three integrations; the estate had seven.
  2. Schedule against operations. The plan proposed a weekend cutover, but depots run around the clock and pharmaceutical consignments move on Sundays. There was no quiet weekend to cut over in.
  3. Cost against scope. The business case licensed 120 users, but the scope put the new driver app in the hands of all 180 drivers, plus controllers.
  4. Acceptance against architecture. The acceptance criteria required temperature data visible to customers within fifteen minutes, while the architecture retained the nightly file transfer for older trailers.

Each contradiction cost a meeting to resolve before the request went out. Found after award, each would have been a change request, a schedule slip or a dispute. The same check is worth running from the supplier side when reading a client's documents, as the hidden architecture of a good proposal argues.

Assumptions become a register, not a paragraph

Most proposals bury assumptions in a paragraph near the end. An evidence-led approach turns them into a register with four fields: the assumption, the evidence behind it, the consequence if it is wrong, and who confirms it. Cedarberg asked bidders to submit assumptions in that format and committed to confirming or correcting each one during clarification.

AssumptionEvidenceIf wrongConfirmed by
Seven integrations in scopeConfiguration exports, health checkEffort and price change per interfaceIntegration owner
Telematics vendor exposes a streaming feedVendor API documentation, version notedIntegration design changesFleet operations head
Cutover can run depot by depotOperations calendarSchedule and staffing changeOperations director
Vehicle-to-trailer record of truth is decided before integration testingGap analysis, conflict still openCustomer view shows the wrong trailerData owner, once named

That table did more to reduce delivery risk than any amount of contingency. It also made the bids comparable, because every supplier was pricing the same confirmed facts. For a fuller treatment of the supplier side, see requirements, assumptions and traceability and the Architecture and Proposal Writing 101 series.

The trade-off

Evidence costs time before the procurement starts, and procurement timetables are often fixed by budget cycles. Cedarberg's evidence file existed because of the health check; an organisation without one has to decide whether a short discovery phase is worth delaying the release. The arithmetic usually favours it: a few weeks of discovery against months of change requests. Where the timetable cannot move, a smaller step still helps. Name the facts the price depends on, mark which are evidenced and which are assumed, and ask bidders to price the assumed ones as options. Discovery protects the date makes the same argument for delivery schedules.

A test for your next request for proposal

Choose the three facts about your current estate that would move the price most if they were wrong. For each, ask where the evidence is, whether every document that depends on it uses the same value, and who will confirm it to bidders. If any of the three has no evidence, you are about to run a procurement on a guess.

Next: Part 6, An audit finding is not a corrective action. All parts are on the series page.

How CloudNala can help

We help organisations establish the current-state facts a procurement depends on, carry them into the request for proposal as traceable assumptions, and check that architecture, scope, schedule, cost and acceptance criteria agree before release. On the supplier side, we review bids so that every line of the estimate can be traced to evidence or to a declared assumption.


Work with CloudNala

CloudNala helps organisations move from technology ambition to practical execution across cloud, AI, data, platform engineering and digital services.

Whether you are exploring AI, modernising your cloud environment, building a public-sector digital service, or turning an idea into a working MVP, we can help you shape the roadmap and deliver the next step.

Book a Technology Health Check or write to us at consult@cloudnala.co.za