Six months into Kowie Mutual's claims-triage project, the numbers looked bad. The fictional insurer's cost per funeral claim had gone up, not down. Assessors were working overtime to check the triage model's suggestions and to run the old process alongside the new one. The chief financial officer wanted to stop. The project sponsor said this was the J-curve: costs first, benefits later.
Both of them could be right. Neither could prove it, because nobody had written down, before the project started, how deep the dip would be, how long it would last or what would show that it was the start of a recovery rather than the start of a failure.
A J-curve is a forecast, not an excuse. Write down the depth, the length and the evidence that would prove it wrong before the dip begins, and review against it on fixed dates.
What the evidence actually says
The phrase comes from economics. Erik Brynjolfsson, Daniel Rock and Chad Syverson's paper The Productivity J-Curve, published in the American Economic Journal: Macroeconomics in January 2021, argued that general-purpose technologies such as AI need large complementary investments in new processes, skills and business models. Many of those investments are intangible and poorly measured, so measured productivity looks too low in the early years and too high later.
The firm-level evidence for AI is newer. The S&P 500 working paper by Yu, Fleming, Hampton, Combemale and Thompson, introduced in part 1, compared firms' net profit margins (net income divided by revenue) with their AI adoption level from 2016 to 2025. Its findings are more careful than the headline:
- Outside the technology sector, firms at the exploring and pilot levels had net profit margins about 2 to 3 percentage points lower than firms with no or minimal adoption, in the authors' main specification. Only the pilot-level estimate was statistically significant. Firms with AI deeply embedded had much higher margins, although few non-technology firms had reached that level.
- Inside the technology sector, the authors did not see a clear J-curve. Margins were higher at most adoption levels.
- With sector-by-year controls, the differences between levels 1 to 4 were no longer statistically significant, although they pointed the same way. The positive association with deep integration remained.
- The results are correlations, as the authors stress. They do not show that AI caused the dip or the recovery. Firms that expected the largest gains may simply have adopted more aggressively.
The MIT Initiative on the Digital Economy's November 2026 summary gives rounder margin figures than the paper's main results. We have used the paper's own numbers and its caveats.
Why the dip happens
The paper's explanation matches what delivery teams see. Costs arrive before benefits. Digital infrastructure, data pipelines, model integration and organisational change are paid for up front, and disruption to existing workflows weighs on results until people and processes adjust.
In a single project, that usually means six costs:
- Integration. Connecting the AI step to the systems that hold the case, the customer and the money.
- Parallel running. Operating the old process alongside the new one until the new one is trusted.
- Review. People checking AI output, often more carefully at first than they will later.
- Rework. Fixing what the AI step got wrong, and what the changed process broke downstream.
- Learning. Training, new procedures and the slower work of people unlearning old habits.
- Error cost. Customers or citizens affected by mistakes, including complaints and remediation.
A dip made of these costs is expected. A dip that keeps growing because review never gets lighter, rework never falls and parallel running never ends is not a J-curve. It is a process that does not work.
The curve is not a licence to wait
Two cautions matter more than the curve itself.
First, the evidence describes firms at different levels, not the same firm over time. Some of the companies at the pilot level will reach deep integration. Others will stay where they are, or go back. The cross-section cannot tell you which group your project is in.
Second, "it is the J-curve" is the easiest thing to say in a review meeting where the numbers are bad. It defers the decision without any new information. CloudNala's When should an organisation stop funding an AI use case? argues that stop, redesign and scale criteria must be agreed before the money is spent. The J-curve template below adds the time dimension: how much worse you agree things may get, for how long, and what must be true at each checkpoint.
The J-curve investment and review template
Complete this before funding a use case expected to cost more before it saves anything. Revisit it at each checkpoint, and do not change the thresholds after the project starts without the sponsor and the finance owner both signing the change.
| Field | What to write | Kowie Mutual (illustrative) |
|---|---|---|
| Outcome and baseline | The measure that must improve, and its current value | Cost per funeral claim; median days to pay |
| Dip budget | The maximum extra cost or performance loss you accept | Up to 15% higher cost per claim for two quarters |
| Expected trough | When the dip should be deepest | Month 4 |
| Time to first usable outcome | When real users first rely on it for real cases | Month 2 |
| Cost to integrate | One-off build and integration cost, kept separate from run cost | Claims-system integration and data clean-up |
| Adoption checkpoint | Share of eligible cases that pass through the AI step | 60% of new claims by month 6 |
| Rework and error measures | Rates measured on a reviewed sample | Override rate under 20% by month 6; no rise in wrongful declines |
| Benefit lag assumption | When benefits should start to appear, and why | Month 7, once parallel running stops |
| Kill criteria | Conditions that stop the project regardless of the forecast | Dip budget exceeded twice; error measure worsens two months running |
| Review dates and owners | Fixed checkpoints and who decides | Months 3, 6 and 9; sponsor and finance owner |
At each checkpoint there are three decisions, not two. Continue if the dip is within budget and the leading measures (adoption, override rate, rework) are moving the right way. Redesign if the dip is within budget but a leading measure is flat, which usually points to the workflow rather than the model; part 3 of this series looks at that. Stop if a kill criterion is met.
What happened at Kowie Mutual
With the template filled in, the six-month review became a short meeting. Cost per claim was 11% above baseline, inside the dip budget. Adoption had reached 64% of new claims. The override rate had fallen from 38% to 19%. Parallel running was due to end in month 7. The decision was to continue, with one change: the finance owner asked for the month 9 review to include the first measured fall in cost per claim, or a stop. The figures are illustrative; the discipline is the point.
What this means for South Africa
For South African organisations, the dip is often deeper than in the studies. Imported software and cloud costs move with the rand, skilled integration capacity is scarce, and the cost of capital is high, so a long dip costs more. Public bodies face a further constraint: budgets are set in annual and medium-term cycles, so a dip that runs past the end of a budget period needs to have been planned for in that budget. A J-curve that nobody wrote into the budget will be read as overspending.
Next in the series: Workflow redesign is the real AI project. Previous: Part 1, Stop counting AI pilots. All parts are on the series page.
Sources and limits: margin findings come from the working paper by Yu, Fleming, Hampton, Combemale and Thompson (arXiv 2607.08920, version 2, November 2026), Section 4 and Table 5, checked on 24 November 2026. The paper has not been peer reviewed, its results are correlations, and it describes large US-listed firms. Its main text and conclusion give slightly different margin figures; we use Section 4. Kowie Mutual and its figures are fictional and illustrative. This is general information, not financial advice.
How CloudNala can help
CloudNala helps sponsors and finance owners agree the shape of an AI investment before it starts. We set the outcome and baseline, estimate integration, review and parallel-running costs, agree the dip budget, leading measures and kill criteria, and run the checkpoint reviews, so that a bad month leads to a decision rather than an argument about curves.
Work with CloudNala
CloudNala helps organisations move from technology ambition to practical execution across cloud, AI, data, platform engineering and digital services.
Whether you are exploring AI, modernising your cloud environment, building a public-sector digital service, or turning an idea into a working MVP, we can help you shape the roadmap and deliver the next step.
Book an AI Portfolio and Benefit-Realisation Review or write to us at consult@cloudnala.co.za