Every plan has a section on what happens if things go well. Few have a section on what would make the team stop. The omission is understandable: at the start, everyone is optimistic, and writing down failure conditions feels like inviting them.
The cost of the omission arrives later. Three months in, the sponsor has moved roles, the budget has been cut and the key integration is harder than expected. Each problem on its own looks survivable. Nobody agreed in advance which combination would be enough to stop, so the work continues by default. Stopping now means someone has to argue for it, against people who have spent three months on the work and want it to succeed.
Teams should write their stopping criteria at the start, while nobody is invested, and check them at every stage: each criterion names a signal, a threshold, a checkpoint date and an owner, and each checkpoint ends in a recorded decision to proceed, pause, reframe or stop.
This is the final part of Qualify Before You Build. The earlier parts each produced a condition that can end an opportunity: an unconfirmed test on the reality board, a material budget mismatch, a failed hard gate, a missing sponsor. This part turns those conditions into a plan.
Why work continues by default
Three forces keep weak work alive.
Sunk cost. The more that has been spent, the harder it is to stop, even though past spending is not a reason to spend more.
Diffuse ownership. When nobody is clearly responsible for calling a stop, everyone waits for someone else to do it.
Moving thresholds. Without written criteria, each new problem is judged against the team's current mood rather than an agreed standard. "Still acceptable" drifts.
Written criteria address all three. They are agreed before costs are sunk, they name who calls the checkpoint, and they fix the threshold before anyone has a reason to move it. CloudNala made the same argument for funded AI use cases in When should an organisation stop funding an AI use case?. This part applies it earlier and more widely: to pursuit, discovery and commitment, not only to delivery.
Four outcomes, at every stage
A checkpoint that can only say "continue" or "stop" will almost always say continue, because stop is too drastic. Four outcomes make the decision more honest:
- Proceed: the criteria are met; move to the next stage.
- Pause: a named condition is not yet met; hold until a set date, then decide again. A pause without a date is a slow stop.
- Reframe: the problem is still worth solving, but the framing is wrong; change the outcome, the scope or the intervention, using the tree from part 2 or the ladder from part 4.
- Stop: end the work, record why, and say what would reopen it, as in part 3's script.
The checkpoints follow the life of the opportunity: after qualification, after discovery, at commitment, and at agreed points in delivery.
The Proceed-Pause-Stop Register
The decision tool for this part is a register, written at the start and reviewed at every checkpoint.
| Condition | Signal | Threshold | Checkpoint | Owner | If breached | Decision and date |
|---|---|---|---|---|---|---|
| Example: sponsor in place | Named sponsor has accepted the role in writing | Confirmed by end of discovery | Discovery close | Delivery lead | Stop, or pause for two weeks while the requester finds one | |
| Example: budget fits | Estimate against the agreed envelope | No material mismatch after refinement | Commitment | Sponsor | Reframe using the Budget-Scope Decision Tree | |
| Example: hard gates | Readiness board status | No gate marked "cannot be met" | Weekly during pursuit | Bid or delivery lead | Decline or partner | |
| Example: outcome evidence | Measured change against the baseline | Agreed movement by an agreed date | First delivery review | Operating owner | Pause and investigate; reframe if not explained | |
Four rules make the register work:
- Write it before the first checkpoint. Criteria written after a problem appears tend to be written around the problem.
- Make thresholds observable. "Strong sponsor support" is not a threshold. "Sponsor has accepted the role in writing" is.
- Name the owner of each checkpoint. That person calls the review and records the outcome, even if the decision belongs to the sponsor.
- Change a threshold only on the record. If a criterion turns out to be wrong, change it explicitly, with the reason, rather than letting it be ignored.
The series on one page
The Opportunity Reality Board brings the series together. Each part contributes one section:
| Part | Question | Tool | Typical stopping condition |
|---|---|---|---|
| 1 | Is the opportunity real? | Opportunity Reality Board | A test blocked, or conditions unresolved by their date |
| 2 | Does the outcome fit the money? | Budget-Scope Decision Tree | Material mismatch with no move the sponsor will choose |
| 3 | How do we decline well? | Responsible No-Go Script | (Used when any other condition is breached) |
| 4 | Is build the right intervention? | Intervention Selection Matrix | Build chosen without evidence against the rungs above |
| 5 | Can every mandatory condition be met? | Hard-Gate Readiness Board | Any gate that cannot be met |
| 6 | Who owns the decision? | Authority Map | Sponsor, budget holder or decision path missing |
| 7 | What would make us stop? | Proceed-Pause-Stop Register | A breached threshold at a checkpoint |
Download the Opportunity Reality Board, a printable worksheet with every tool from the series.
The illustrative AI platform request, closed out
The illustrative organisation's request began as "an AI platform" and, over the series, became a configure-and-integrate project for status messages, with a named operations sponsor, an agreed envelope and a recorded option for a later model step. Its register, written at the end of discovery, included a stopping condition for that later option: if configured messages did not reduce repeat status calls by an agreed amount within an agreed period, the model step would not be funded, because the problem would not be what the team thought it was. The amounts are the organisation's to set. The point is that they were set before the work started, by the people who would later have to apply them.
What this means for South Africa
South African organisations, particularly in the public sector, often find it easier to start work than to stop it, because stopping can look like failure in an audit or a performance review. Written stopping criteria change that: a stop made against a criterion agreed in advance is evidence of control, not of failure. Earlier CloudNala series made the same point for AI pilots, notably The AI value J-curve, which argued that the dip should be planned. A later series, Discovery Is Decision Infrastructure, picks up from here, with what discovery must deliver so that the first checkpoint has evidence to read.
How CloudNala can help
CloudNala's Opportunity Reality Assessment ends with a Proceed-Pause-Stop Register agreed with the sponsor. We draft criteria from the reality board, the budget decision, the hard gates and the Authority Map, make each threshold observable, name the checkpoint owners and set the dates. Where work is already under way without criteria, we help write them now, and run the first checkpoint against them.
This is the final part of Qualify Before You Build. Previous: Part 6, Who owns the decision? All parts are on the series page.
Sources and limits: the four outcomes, the register, its rules and the series summary are CloudNala analysis and recommendation. The AI platform request is an illustrative composite and no thresholds are given for it. This part makes no external factual claims.
Work with CloudNala
CloudNala helps organisations move from technology ambition to practical execution across cloud, AI, data, platform engineering and digital services.
Whether you are exploring AI, modernising your cloud environment, building a public-sector digital service, or turning an idea into a working MVP, we can help you shape the roadmap and deliver the next step.
Book an Opportunity Reality Assessment or write to us at consult@cloudnala.co.za